A foam and mattress manufacturer in Libya upgraded its existing batch foaming system to a 16-component continuous foaming line. Sabtech also supplied the client with a vertical foam cutting machine, mattress materials, and foaming raw materials.
The production line officially entered operation in September 2024, achieving an actual output of approximately 500 cubic meters per day and exceeding the client’s expectations.
The client manufactures both flexible PU foam and mattresses and previously used a batch foam machine for foam production. As production demand increased, the existing system gradually presented several problems:
The client therefore decided to replace the existing foaming equipment and upgrade from batch foaming to continuous production to improve production stability, capacity, and automation.
The client’s main concern was whether its team could master the operation and production control of a continuous foaming line. Continuous foaming requires coordination between raw material metering and delivery, mixing, foam rise, and conveyor speed, making its operating method different from that of a batch foam machine.
Before confirming the order, the client compared several suppliers, focusing on initial investment, equipment stability, automation level, and technical support.
Through remote meetings and video demonstrations, Sabtech introduced the equipment structure, operating method, and project support arrangements. The client then visited Sabtech’s factory in China for an on-site inspection and further discussions with the technical team.
Professional communication, timely responses, and ongoing technical support were important reasons why the client ultimately chose Sabtech.
The client’s initial order included:
The continuous foaming line was intended to improve foam production stability, capacity, and automation. The vertical cutting machine supported subsequent foam cutting, while the foaming raw materials and mattress materials supported the client’s foam and mattress production.
The client did not initially specify a 16-component configuration. Sabtech proposed this solution based on the client’s daily output requirements, color requirements, and production cost-control needs.
The configuration was selected for three main reasons:
The 16-component configuration included:
The production line uses a PLC control system, allowing operators to centrally set and manage production parameters and equipment operation through the control interface.
The line is also equipped with a foam height monitoring function, enabling operators to observe changes in foam height and monitor the foaming condition.
Project discussions began in October 2023. The main implementation stages were:
Sabtech engineers completed the installation and commissioning at the client’s factory. Training covered equipment operation, routine maintenance, basic troubleshooting, production process coordination, safety precautions, and formulation adjustment, helping the client’s team adapt to the production requirements of the continuous foaming line.
The continuous foaming line officially entered production in September 2024, achieving an actual output of approximately 500 cubic meters per day and exceeding the client’s expectations.
Based on its performance after start-up, the line has maintained stable control of key parameters, including raw material ratios, temperature, and finished foam density, during extended continuous operation. This has improved production stability and efficiency.
The estimated investment payback period for the project is approximately three years.
After the project entered operation, the client continued to purchase the following products from Sabtech:
These subsequent purchases further strengthened the client’s production setup and continued to support the material requirements of its foam and mattress production.
This project is particularly relevant to foam and mattress manufacturers that:
The core of this project was the transition from the client’s existing batch foaming system to continuous production. In addition to replacing the equipment, the client also needed to adapt its operating methods, formulation adjustment, and production management to the requirements of continuous production.
For manufacturers planning a similar upgrade, the equipment solution should be evaluated based on production requirements, product types, operator capabilities, raw material supply, technical training, and ongoing production support.
Just leave your email or phone number in the contact form so we can send you a free proposal!
Contact Person: Cynthia Cheung
Contact Number: +86-15687268672
Email: sales@alforu.cn
WhatsApp: +86-15687268672
Company Address: Foshan City, Guangdong Province China